“Pasig City Hope Medical Center”
MAIN OBJECTIVE: To add more medical services. Mas marami itong masisilbihan na Pasigueño bilang general hospital.
HIGHLIGHTS:
1. Expansion of ER;
2. Expansion for adult medical, surgical and OB-GYN services;
3. Improvement of of Pediatric services.
The building is 7 floors plus basement and upper roof deck. 1,600 sqm building foot print, 12,800 sqm floor area
600 days ang construction period nito (total ~315M).
MORE DETAILS ON THE SCOPE OF WORK
Additional rooms/works as per DOH standards, INCLUDING:
1. Extension of Emergency Room (from 4 beds to 13 beds plus 5 beds treatment and isolation area)
2. Pediatric and medical ICU (from 9 beds to 13 beds) and 15 beds for neonatal ICU
3. 2 bed Labor Room and 2 bed High-risk Pregnancy Unit
4. 3 beds, Delivery Room
5. New 2 Operating Rooms and Recovery Room
6. Sterilization/ Autoclave Room
7. Blood Bank Unit
8. 12 units for Hemodialysis
9. Additional 3 beds room at ward extension and rehabilitation of all ward
10. 12 bed ward extension at lower deck
11. Social Service Section
12. Additional 4 treatment areas for Physical Therapy Section
13. Improvement of Pharmacy
14. Improvement of Dietary and Nutrition Clinic at lower deck
15. Extension of Clinical and Molecular Laboratory
16. Additional Nurse Stations
17. Doctor’s quarters at lower deck
18. Improvement of Diagnostic and Radiology Rooms
19. New Admitting Counters
20. Finance Department room
21. Recovery Room
22. Sterile Room
23. Storage Facility at basement
24. Replacement of Ceiling
25. Waterproofing of basement, ledges, roof deck and upper decks and all other leaks
26. Flooring: Industrial Power floor self leveling compound and homogenous anti-bacterial Vinyl Roll with cove former, capping strip, etc.
27. Modular work stations
28. Built-up cabinets
29. Improvement of all comfort rooms
30. Medical Gas Piping
31. Plumbing Works (water lines and sewerage lines)
32. Electrical Works (upgrading, rewiring, and replacement of fixtures)
33. Mechanical Works (Air-conditioning of entire building – VRF)
34. Fire Detection and Alarm System (FDAS)
35. CCTV) system
35. Public Address System
36. Building Management System
#PasigCity #ChildsHope #PasigHope